Mumbai Coastal Road North Project Gains Momentum As Dahisar-Bhayandar Link Road Moves Towards 2028 Completion

Mumbai Coastal Road North Project Gains Momentum As Dahisar-Bhayandar Link Road Moves Towards 2028 Completion
Kort samengevat

The Dahisar-Bhayandar Link Road, the final stretch of Mumbai Coastal Road (North), has entered a key construction phase with piling and pile-cap work underway. BMC officials said 60 piles, five pile caps and nine bridge segments have been completed. Launching-girder work is scheduled from October as the project targets completion by December 2028.